备件仓库II Spare part storage II(102)| 文件编号 | 2252 | 工期 | 499天 | 开始时间 | 2018-04-20 | 结束时间 | 2019-08-31 |
| 任务数 | 23K | 整理日期 | 2019/5/17 | 下载次数 | 3920次 | ||
| 下载地址 | 计划文件点击下载(登录后才可以下载) | ||||||
| 备件仓库II Spare part storage II(102) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
编号 |
任务名称 |
工期 |
开始时间 |
结束时间 |
前置任务 |
资源名称 |
| 1 | 总工期 |
499天 | 2018-04-20 | 2019-08-31 | ||
| 2 | E0工作节点下的相关工作 Related work at E0 working node |
162天 | 2018-04-20 | 2018-09-28 | ||
| 3 | 1.地基与基础 Ground and foundation |
36天 | 2018-04-20 | 2018-05-25 | ||
| 4 | 2.主体结构完成(含钢结构) Completion of main structure (including steel structure) |
82天 | 2018-05-26 | 2018-08-15 | ||
| 5 | 3.屋顶作业防水外墙内墙(结构)Roof work, and external and internal waterproof wall (structure) |
47天 | 2018-07-10 | 2018-08-25 | ||
| 6 | 4.工艺设备地基、地台完成固化 Solidification of process equipment foundation and platform |
23天 | 2018-08-10 | 2018-09-01 | ||
| 7 | 5.工艺设备的完整性和形貌检查等 Process equipment integrity and morphology inspection |
15天 | 2018-09-01 | 2018-09-15 | ||
| 8 | 6.其他情形下的施工任务 Construction tasks under other circumstances |
19天 | 2018-09-10 | 2018-09-28 | ||
| 9 | E1工作节点下的相关工作 Related work at E1 working node |
99天 | 2018-08-15 | 2018-11-21 | ||
| 10 | 1.室内建筑照明及工艺安装电源 Power source for indoor building lighting and process installation |
67天 | 2018-08-15 | 2018-10-20 | ||
| 11 | 2.建筑施工完成 Completion of building construction |
81天 | 2018-09-01 | 2018-11-20 | ||
| 12 | 3.其他非建筑内配套工程 Other auxiliary works outside the building |
43天 | 2018-10-10 | 2018-11-21 | ||
| 13 | E2工作节点下的相关工作 Related work at E2 working node |
114天 | 2018-09-05 | 2018-12-27 | ||
| 14 | 1.完成所涉的管道系统压力测试液体和管道的冲洗 Relevant pipe system pressure test liquid |
97天 | 2018-09-10 | 2018-12-15 | ||
| 15 | 2.电信网络接通、电源接通 Telecommunication network connection and power source connection |
82天 | 2018-09-05 | 2018-11-25 | ||
| 16 | 3.相关通风系统开始运行 Relevant ventilation system operation |
92天 | 2018-09-10 | 2018-12-10 | ||
| 17 | 4.灭火检测、火警系统正常运作交付 Fire extinction detection, and normal operation and handover of fire alarm system |
97天 | 2018-09-15 | 2018-12-20 | ||
| 18 | 5.其他配套事项 Other auxiliary items |
38天 | 2018-11-20 | 2018-12-27 | ||
| 19 | E3工作节点下的相关工作 Related work at E3 working node |
165天 | 2019-03-20 | 2019-08-31 | ||
| 20 | 1.完成承包商所建筑中的扫尾事项 Completion of outstanding work in the Contractor's construction |
32天 | 2019-03-20 | 2019-04-20 | ||
| 21 | 2.完成清理工作、包括拆除临时设施 Completion of cleaning work, including removal of temporary facilities |
20天 | 2019-04-21 | 2019-05-10 | ||
| 22 | 3.提交竣工资料等相关手续 Submission of completion data and other relevant formalities |
32天 | 2019-05-10 | 2019-06-10 | ||
| 23 | 4.竣工交付类相关事项 Completion, handover and relevant similar items |
88天 | 2019-06-05 | 2019-08-31 |