 TM1608&1609Construction Schedule

TM1608&1609Construction Schedule

文件编号 17581 工期 395天 开始时间 2016-04-19 结束时间 2017-05-18
任务数 87K 整理日期 2019/5/17 下载次数 4102
下载地址 计划文件点击下载(登录后才可以下载)
计划内容
TM1608&1609Construction Schedule

编号

Item No.

Construction Period

Starting date

Finishing Date

前置任务

资源名称

1
Contract sign
1天 2016-04-19 2016-04-19    
2
Effective date of the contract
1天 2016-05-25 2016-05-25    
3
Design
105天 2016-06-08 2016-09-20    
4
Drawings for approval
118天 2016-06-28 2016-10-23    
5
Steel cutting
1天 2016-07-13 2016-07-13    
6
Hull Construction
228天 2016-07-13 2017-02-25    
7
Main hull Blocks fabrication
120天 2016-07-13 2016-11-09    
8
Accommodation Blocks fabrication
60天 2016-11-02 2016-12-31    
9
Blocks assembly
90天 2016-11-09 2017-02-06    
10
Seats for equipments
60天 2016-12-14 2017-02-11    
11
Support for equipments
60天 2016-12-28 2017-02-25    
12
Tanks inspection
50天 2017-01-04 2017-02-22    
13
NDT
50天 2016-11-02 2016-12-21    
14
Air test
50天 2016-11-16 2017-01-04    
15
Painting
258天 2016-08-10 2017-04-24    
16
Blocks
130天 2016-08-10 2016-12-17    
17
Painting defects fold up
160天 2016-11-16 2017-04-24    
18
Fresh water tank
30天 2017-01-11 2017-02-09    
19
Oil tank
20天 2017-01-18 2017-02-06    
20
Launching
1天 2017-03-15 2017-03-15    
21
Main engine(propulsion system)
76天 2016-12-14 2017-02-27    
22
Seating and support
10天 2016-12-14 2016-12-23    
23
Installation
30天 2017-01-25 2017-02-23    
24
Commissioning
5天 2017-02-23 2017-02-27    
25
Generator sets
92天 2016-12-07 2017-03-08    
26
Generator seat and support
31天 2016-12-07 2017-01-06    
27
Generator installaion
5天 2017-01-18 2017-01-22    
28
Cables installation
25天 2017-01-02 2017-01-26    
29
Commissioning
15天 2017-02-22 2017-03-08    
30
Mooring winches
96天 2016-12-28 2017-04-02    
31
Winches foundation
48天 2016-12-28 2017-02-13    
32
Winches installation
18天 2017-02-09 2017-02-26    
33
Cables installation
16天 2017-02-24 2017-03-11    
34
Commissioning
12天 2017-03-22 2017-04-02    
35
Anchor Winches
138天 2016-12-07 2017-04-23    
36
Winches foundation
138天 2016-12-07 2017-04-23    
37
Winches installation
18天 2017-02-01 2017-02-18    
38
Cables installation
16天 2017-02-09 2017-02-24    
39
Chain installtion
5天 2017-03-01 2017-03-05    
40
Anchor installation
2天 2017-03-22 2017-03-23    
41
Commissioning
4天 2017-03-26 2017-03-29    
42
Sewage equipments
93天 2016-11-25 2017-02-25    
43
Seat and foundation
16天 2016-11-25 2016-12-10    
44
Installation
14天 2016-12-13 2016-12-26    
45
Commissioning
16天 2017-02-10 2017-02-25    
46
Fresh water maker and sterilizer
92天 2016-11-26 2017-02-25    
47
Seat and foundation
20天 2016-11-26 2016-12-15    
48
Installation
5天 2016-12-21 2016-12-25    
49
Commissioning
16天 2017-02-10 2017-02-25    
50
Pumps
124天 2016-10-01 2017-02-01    
51
Seat and foundation
26天 2016-10-01 2016-10-26    
52
Installation
55天 2016-10-07 2016-11-30    
53
Commissioning
24天 2017-01-09 2017-02-01    
54
Pressure tanks
47天 2016-12-24 2017-02-08    
55
Seat and foundation
12天 2016-12-24 2017-01-04    
56
Installation
6天 2017-01-13 2017-01-18    
57
Commissioning
17天 2017-01-23 2017-02-08    
58
Fans
42天 2017-01-30 2017-03-12    
59
Installation
21天 2017-01-30 2017-02-19    
60
Commissioning
12天 2017-03-01 2017-03-12    
61
MGPS
47天 2016-12-21 2017-02-05    
62
Seat and foundation
5天 2016-12-21 2016-12-25    
63
Installation
12天 2016-12-24 2017-01-04    
64
Commissioning
5天 2017-02-01 2017-02-05    
65
AC
58天 2017-02-08 2017-04-06    
66
Installation
24天 2017-02-08 2017-03-03    
67
Cables connection
12天 2017-02-22 2017-03-05    
68
Commissioning
16天 2017-03-22 2017-04-06    
69
MSB
88天 2017-01-02 2017-03-30    
70
Installation
5天 2017-01-18 2017-01-22    
71
Cables connection
25天 2017-01-02 2017-01-26    
72
Commissioning
23天 2017-03-08 2017-03-30    
73
Outfitting items
60天 2017-02-11 2017-04-11    
74
Piping supply
33天 2017-02-18 2017-03-22    
75
sanitary unit
12天 2017-02-11 2017-02-22    
76
Laundry equipment
19天 2017-03-03 2017-03-21    
77
Room pannel
20天 2017-03-10 2017-03-29    
78
Deck cover
19天 2017-03-17 2017-04-04    
79
Light etc.
33天 2017-03-10 2017-04-11    
80
Electrical reference
46天 2017-02-26 2017-04-12    
81
Normal light
33天 2017-03-10 2017-04-11    
82
FIRE ALARM / GENERAL ALARM
12天 2017-03-11 2017-03-22    
83
NAVIGATION / WIRELESS EQUIPMENT
6天 2017-03-17 2017-03-22    
84
INNER COMMUNICATION EQUIPMENT
12天 2017-04-01 2017-04-12    
85
CONTROL BOX
26天 2017-02-26 2017-03-23    
86
Sea trial
8天 2017-04-27 2017-05-04    
87
Delivery
2天 2017-05-17 2017-05-18    